San Vicente Gas Terminal

PRDW participated in the definition of a preliminary structural project for the EPC bid. After the appointment, the detail design engineering and complementary studies were executed.

The marine works project included the design of a 2.2km access trestle, the unloading platform, 4 breasting dolphins, 4 mooring dolphins and gangways. Besides the structural design of all the marine works.

PRDW executed the following studies and activities:

  • Numerical modeling of the ship at berth dynamics.
  • Reformulation of the berth area.
  • Reformulation of the levels of the structure.
  • Hydrodynamic loads along the access trestle and berth area.
  • Supervision and coordination of the soil mechanics studies, maneuvering and navigation aids and field measurements.